Fermi

Jan 29, 2026

Just spitballing with Gemini + GPT on FRMI - - no format just thrown together some thoughts... all eyes on Rick Perry landing a deal... will add and edit on the go

image

Fermi America (FRMI): The “Behind-the-Meter” AI Power Play

The Core Idea

Fermi America is not selling electricity.
They are selling time, certainty, and scale in an era where power — not GPUs — is the bottleneck for AI.

The company’s strategy is simple but extremely rare:
build massive, private, behind-the-meter power plants (gas → nuclear) directly next to hyperscale AI data centers, bypassing the public grid entirely.

In a world where grid interconnection now takes 5–8 years, Fermi’s value proposition is the ability to deliver gigawatt-scale power in months, not years

Hyperscalers need power and land, fermi lets them rent the land to use the power.. they’re the landlord

What “Behind-the-Meter” Actually Means

Fermi builds power on the same side of the meter as the data center:

  • On-site natural gas turbines today

  • On-site nuclear (AP1000s) later

  • Private wires, private cooling, private control

This completely bypasses ERCOT and the public utility grid.

Why it matters:
Hyperscalers are no longer power-constrained by capital — they’re constrained by interconnection queues, permitting delays, and transmission build-outs. Fermi collapses that entire timeline.

Project Matador: The Physical Asset

  • Location: Carson County, ~12 miles NE of Amarillo, Texas

  • Land: 5,800 acres (leased from Texas Tech University System)

  • Scale: Planned 11 GW total (gas + nuclear + solar + storage)

  • Security: Adjacent to Pantex (U.S. nuclear weapons facility)

  • Fuel: Direct access to Energy Transfer & ONEOK pipelines + Permian Basin

  • Fiber: One of the densest long-haul fiber intersections in the U.S.

  • Water: Ogallala Aquifer + hybrid closed-loop cooling strategy

This is not a speculative site. It is one of the best-positioned energy + data center locations in North America.

The 3-Phase Power Strategy

Phase 1 — Speed (Now → 2026)

  • Natural gas turbines (Siemens SGT6-5000F / GTM2500)

  • Target: ~1.1 GW online by end of 2026

  • Purpose: Win tenants who need power immediately

Phase 2 — Scale (2026–2030)

  • Additional gas + solar + storage

  • Multi-tenant hyperscale campus

  • Purpose: Absorb overflow demand from grid-constrained regions (VA, OH, TX)

Phase 3 — Moat (2030+)

  • Nuclear (Westinghouse AP1000)

  • Cheapest, cleanest, baseload power

  • Purpose: Make grid-dependent competitors structurally obsolete

Why Siemens Is the Smoking Gun

Fermi’s September 2025 LOI with Siemens Energy was not for backup generators.

It was for:

  • Three SGT-800 turbines (1.1 GW class)

    • lead times for these machines go through 2+ years out but they skipped line by making a deal with Firebird LNG

  • Industrial, 24/7 baseload machines

  • The exact turbines required to power liquid-cooled AI factories

Siemens + NVIDIA + nVent have standardized liquid cooling architectures for Blackwell (GB200) clusters.

That matters because only AI-factory tenants need:

  • Liquid Cooling Distribution Units (CDUs)

  • F-class turbines

  • Private grid stabilization (battery + BlueVault)

This hardware stack rules out traditional hyperscalers and strongly points to AI-first tenants.

image

image

Tenant-by-Tenant Fit

image

xAI / SpaceX — The Speed-First Wildcard

(Current favorite to land FRMI)

Why it fits

  • Colossus-class clusters have repeatedly shown willingness to use non-standard, gas-heavy, behind-the-meter power.

  • Texas-centric, high tolerance for unconventional infrastructure and operational secrecy.

  • History of parallel site development to avoid single-point bottlenecks.

  • Project Matador’s gas-first ramp (1–1.5 GW by YE 2027) aligns with their demonstrated urgency better than pure nuclear plays.

Google — The Long-Term, Nuclear-Aligned Fit

Why it fits

  • Massive, confirmed Texas expansion ($40B+ commitment through 2027).

  • Actively building in the broader Panhandle (Meitner Energy Center in Gray/Roberts Counties near Pampa, plus other sites).

  • Public emphasis on co-located clean power and long-term baseload.

  • Hiring patterns and site-level ops activity in the region support ongoing evaluation of additional capacity.

Microsoft — The Sovereign-Scale Option

Why it fits

  • One of the few counterparties that can credibly absorb multi-GW campuses.

  • Clear interest in sovereign/secure AI infrastructure and nuclear (TerraPower adjacency exists via broader industry networks).

  • Balance-sheet capacity and long-duration contracting appetite match Project Matador’s scale.

Meta — The "Sovereign Utility" Visionary

Meta is moving beyond power purchase agreements to become the financial architect of a complete, vertically integrated nuclear supply chain in the U.S..

  • TerraPower–Meta agreement (Jan 2026) for up to 8 Natrium reactors (~2.8 GW baseload, up to 4 GW with storage).

  • ASPI / Quantum Leap Energy (QLE) has HALEU supply agreements with TerraPower.

  • August 2025 non-binding MOU between ASPI/QLE and Fermi America to explore a HALEU enrichment JV at the Project Matador site.

  • QLE established global HQ in Austin (Feb 2026) and continues to reference the Fermi collaboration.

  • Lee McIntire sits on the Fermi board; he previously served as CEO of TerraPower (2015–2018) and held senior roles at Bechtel.

This creates a potential “sovereign loop”: Meta’s reactors need HALEU → ASPI/QLE produces it → potential co-location or offtake at Matador → Meta data centers on the same private grid. McIntire provides a credible personal bridge between reactor technology, industrial construction, and Fermi.

image

Anthropic — The 10GW Sovereign Compute Match

Why Anthropic fits:

  • Stated need for ~10GW to train next-generation frontier models

  • Fermi America’s Project Matador is engineered for ~11GW of dedicated, private-grid power in a single location

  • One of the only projects globally matching Anthropic’s power requirement 1-for-1, without multi-site stitching

  • Pursuing self-performed data center capacity, not just renting from Amazon or Google

  • Shared West Texas geography: Abernathy site (Hale County) sits ~60 miles from Matador along the I-27 corridor

  • Likely overlap on Hugoton Basin gas, Panhandle wind/solar, and high-voltage transmission infrastructure

  • Safety-first, control-oriented culture aligns with fenced, single-tenant, private-grid campuses

CoreWeave — The Best Timing Fit

Why they match Matador almost perfectly:

  • ~$56B AI compute backlog already signed

  • Public goal to bring 1+ GW online by 2026

  • Already deploying behind-the-meter natural gas in Texas (“Project Horizon”)

  • Designed around liquid-cooled NVIDIA Blackwell (GB200) clusters

  • Received $2B from NVIDIA (Jan 27, 2026) specifically to accelerate land + power

Key point:
CoreWeave’s constraint is not capital — it’s power delivery speed.

Why the First Tenant Matters So Much

The December 2025 loss of the initial tenant wasn’t about $150M.

It was about anchor risk:

  • The first tenant validates the entire 1.1 GW timeline

  • Losing them created a funding gap and execution fear

  • That’s why the stock collapsed ~40%

Crucially:

  • No cash was drawn

  • No debt was incurred

  • The exclusivity window simply expired

This happens in large infrastructure deals — unless the timeline slips, which is what the market feared.

The March 2026 Pressure Cooker

Three clocks are ticking simultaneously:

1. Bonus Window (Jan–Mar 15)

CFO / COO bonuses (up to 200% cash + equity) depend on:

  • Gas interconnect in service

  • Power-on milestones

  • Visible execution progress

2. Lawsuit Deadline (Mar 6)

Lead plaintiff deadline in the securities class action.
Management is heavily incentivized to announce a tenant or major validation before this date.

image

image

3. Lock-Up Expiration (Mar 30)

First day insiders can sell.
If no tenant exists, the market assumes selling pressure.
If a tenant does exist and insiders hold → massive signal.

image

Why Rick Perry Matters

Rick Perry is not the dealmaker — he is the enabler.

He:

  • Guarantees fuel certainty (Energy Transfer)

  • Opens Texas regulatory doors

  • Aligns the project with DoD / DOE priorities

  • Makes nuclear credible long-term

But urgency selects the tenant, not Perry.

The Tenant Selection Reality

This is not ideological — it’s logistical.

image

Fermi is intentionally tenant-agnostic:

  • Gas now

  • Nuclear later

  • Private grid always

That flexibility is the asset.

Water: The Real Risk

Fermi’s biggest long-term challenge is water optics.

Current reality:

  • Approved for 2.5M gallons/day from Amarillo (expensive, controversial)

  • Hybrid closed-loop cooling planned (80%+ reduction)

  • Long-term recycled water + dry cooling roadmap

The risk is perception, not immediate feasibility — but it will matter if the cooling tech underdelivers.

REIT Structure (Often Overlooked)

Fermi is a REIT.

That means:

  • Must distribute ≥90% of taxable income

  • Once profitable → dividends

  • Infrastructure-style valuation once stabilized

Job Listings

As of late January and early February 2026, Fermi LLC (the operational arm) has posted several high-level, specialized roles that suggest the project is moving past the "dirt moving" phase and into the "power delivery" phase:

image

https://recruiting.paylocity.com/recruiting/jobs/All/add565e9-4cee-4334-8182-9de221ffb9e4/Fermi-LLC


Eaton

image

image

image

Construction & Execution Capability

  • Large-scale AI campuses fail more often due to execution bottlenecks than capital constraints.

  • Fermi addresses this risk directly through Stefan Kasan, AI Data Center Lead.

  • 21 years total construction experience; 12 years specifically in data center builds.

  • Former campus construction manager for Meta Platforms, including delivery of Nebraska hyperscale facilities.

  • Brings firsthand experience in:

    • Multi-building campus sequencing

    • Power + cooling coordination

    • Contractor stack management

    • Commissioning and handoff under aggressive timelines

  • This fills a critical gap on the executive team: hyperscale delivery, not just site acquisition or power theory.

Local Governance, Water, and Permitting Risk

  • Community opposition and water rights are the most common derailment risks for Texas data center projects.

  • Fermi mitigated this early by appointing Trent Sisemore as Community Lead.

  • Sisemore is:

    • Former Mayor of Amarillo (2001–2005)

    • Fourth-generation Amarillo resident

    • Previously retained by Rick Perry as an independent consultant

  • Track record includes:

    • Securing long-term municipal water rights

    • Managing large civic infrastructure projects

    • Navigating federal, state, and local regulatory coordination

  • His role materially lowers:

    • Water-access uncertainty

    • Local political resistance

    • Permitting and inter-agency delay risk

  • This is especially relevant given Matador’s proximity to sensitive federal facilities and reliance on hybrid cooling strategies.

Important watch:

"Secretary of Energy has Fermi's plans on his wall" - Trent

Traded land with Pantex and went through 28 regulatory agencies and only took 45 days when it should have took 6 years... PRIORITY

Capital Structure + Korean Industrial Alignment

  • Fermi’s build partners are concentrated among major South Korean industrial firms:

    • Nuclear components: Doosan Enerbility

    • Construction: Hyundai E&C, Samsung C&T

    • Grid and transformers: HD Hyundai Electric, LS Electric

  • This aligns with recent U.S.–Korea agreements committing large-scale Korean capital to U.S. nuclear and energy infrastructure.

  • Under this framework:

    • Capital is deployed geopolitically, not purely commercially

    • Korean funding flows to Korean builders executing U.S.-based strategic projects

    • Long-term profit participation is shared rather than front-loaded

  • Fermi acts as the project vehicle, not the capital source — reducing near-term balance-sheet strain.

  • This helps explain why major partners are willing to commit before tenant announcements or advance funding.

Underwriting & Strategic Oversight

  • Fermi’s IPO is underwritten by Cantor Fitzgerald.

  • Cantor’s involvement has drawn scrutiny due to Howard Lutnick’s former leadership role at the firm.

  • Regardless of optics, the practical implication is:

    • Strong institutional access

    • Deep experience in infrastructure-heavy, politically sensitive transactions

    • Familiarity with national-security-adjacent projects

  • The underwriting choice reinforces the view that Fermi is being positioned closer to strategic infrastructure than a conventional power or data center REIT.


A late 2025 agreement where Japan ($550B) and South Korea ($200B) pledged massive funds for U.S. nuclear infrastructure. Fermi's plan to use Westinghouse AP1000 reactors makes it a prime candidate for this capital.

image

image

image

imageThe Uzman Effect

image

Milestones + partners

image

https://investor.fermiamerica.com/?_gl=1*1p9ujim*_ga*NDc3MDg4MTc1LjE3Njc5MDQ4ODY.*_ga_6DEFPJFQKZ*czE3Njk3MTc0NzgkbzckZzAkdDE3Njk3MTc0ODAkajU4JGwwJGgw

image

imageimage

Nearby Job Listings

imageWho to watch for

image

image

image

imageGovernor Greg Abbott

image

image

Coreweave competitor or tenant??

image

image

image

image

image

image

image

image

image

image

Key Executives

image

imageBoard

image

image

image

image

image

image

image

image

Breaking down incentives

image

image

image

imageMilestones for incentives

image

image

image

FRMI is a REIT
meaning once profitable there will be a divvy

"We will be required to distribute at least 90% of our REIT taxable income"

image

image

Lawsuit

image

image

image

image

Rick Perry Interview

@ 41:00 they talk about Fermi for about 5 minutes

From Rick himself on how FRMI started..

Ricks son, Giffin, & Toby live near eachother and walk 3 out of 7 days together and one day came up with Behing the Meter power solution for ai data center project

The property location is the key

Right next to the DoE in Amirillo Tx

Texas Tech owns the 5800 acres - - interstate highway that runs by the southern side with a rail line that follows

one of largest fiber networks in united states running both through and around the site

2 12 inch gas lines - - Energy Transfer & Oneok

planning 24 inch line from the site down to the Permian - - so sitting on largest gas field in America + second largest aquifer (water)

everything you need to build this is right there already

this project is going to be 50% BIGGER than the BIGGEST data center known today

image

image

image

image

image

image

Fiber

image

Water shortage??

image

image

image

Ricks response about water

https://www.texastribune.org/2025/10/02/rural-texas-data-centers-water/#:~:text=Data%20centers%20are%20thirsty%20for,25%2C%202025